Zhuhai Jianan Group Co., Ltd. was established in 1987. In 1996, it was promoted to a state-level construction enterprise. It is the only municipal state-owned grade A construction general contracting enterprise in Zhuhai City.

The company has a number of contracting qualifications, including grade A general contracting of building construction work, grade A general contracting of municipal public construction work, grade A professional contracting of mechanical and electrical equipment installation, grade A professional contracting of building decoration engineering, grade B professional contracting of building curtain wall engineering, grade B professional contracting of steel structure engineering, grade C professional contracting of foundation and foundation engineering, grade C qualification for real estate development and grade B qualification for architectural decoration design.

Project Name:

Fukang Garden Phase II

Development unit:

Zhuhai Special Economic Zone Zhuguang House Property Development Co., Ltd.

Designing Unit:

Zhuhai Architecture Design Institute

Supervising unit:

Zhuhai Construction Supervision Co., Ltd

Surveying Unit:

China Nonferrous Metal Industry’s Changsha Survey and Design Institute Co., Ltd.

Quality Supervising Unit:

Zhuhai Construction Quality and Safety Supervision Station

Safety Supervising Unit:

General Contracting Unit:

Zhuhai Jianan Group Co., Ltd.

The second phase of Fukang Garden is located on the east side of Yingbin North Road, Xiangzhou District, Zhuhai, and on the south side of the Shizhuyuan Community. This project comprises two high-rise residential buildings with a gross floor area of 24,353.15 m2, 1 basement, and 20 stories above ground for No. 9 and No.10 buildings in a reinforced concrete shear wall structure. The total investment of the project is 120 million yuan.

The foundation is made of prestressed concrete cylinder pipe piles. The internal and external walls are made of autoclaved aerated concrete masonry units bond by M5.0 cement mortar, with aluminum alloy sliding windows and 5/6 mm clear tempered glass. Basement and exterior waterproofing are made of polyurethane waterproof coating.

The commencement date was March 1, 2013 and the completion date was April 28, 2017.